Contract No. HY/2009/19 — Central - Wan Chai Bypass — Tunnel (North Point Section) and Island Eastern Corridor Link

 




Workfront on the spot – View from Sea View Estate, North Point






Works progress (New reclaimed land adjacent to Watson Road, North Point) – Construction of roof slab for tunnel structure






Works progress (Works site adjacent to Victoria Centre, North Point) – Excavation works at East Ventilation Building






Works progress (New reclaimed land adjacent to Watson Road, North Point) – Construction of pier






Works progress (Works site adjacent to The Harbour Grand Hong Kong Hotel) – Construction of bored pile for Tunnel Approach Ramp






Works progress (Works Site adjacent to Oil Street, North Point) – Installation of pre-bored H-pile for foundation of Administration Building






Works progress (Works site adjacent to Victoria Centre, North Point) – Erection of precast beam for new Island Eastern Corridor bridge (eastbound)






Works progress (Adjacent to Block 8 of Provident Centre, North Point) – Construction of dolphin pile cap for new Island Eastern Corridor bridge (eastbound)






Works progress (Works site adjacent to The Harbour Grand Hong Kong Hotel) – Segmental launching of precast bridge segments






Works progress (Works site at Watson Road, North Point) – Road reinstatement works